• Installation of fencing and site-clearing work will begin this Saturday, Feb. 9.
  • Bulk demolition of the houses will begin Monday morning, Feb. 11. The total demolition process is anticipated to take 2-3 weeks.
  • A webcam is being installed, and we will provide the link when it’s set up.
  • McCartney Street will be closed to traffic 7 a.m. to 5 p.m. beginning Saturday, Feb. 9, through (and including) Thursday, Feb. 14. It will be open 5 p.m. to 7 a.m. on those days.
  • Access through Marquis Alley will be closed from Saturday, Feb. 9, through the end of the project in August 2020.